When you book
- Get the load's weight and size from the supplier, builder or manufacturer.
- Send photos of the street, the driveway or gate, and where the load is going.
- Measure the narrowest point the crane has to pass, like a gate or a gap between buildings.
- Tell us if the crane may need to set up on the road, so we can sort a council permit.
A few days before
- Make sure the slab, footings, stumps or stand are ready for the load.
- Let neighbours know if the street or a shared driveway will be busy.
- Trim or tie back branches that hang over the access path or the lift area, where you're allowed to.
- Tell us about septic tanks, pits, pipes or recent trenches under the access path.
On the day
- Move cars, trailers and bins out of the driveway and off the street out the front.
- Clear the path and the drop zone of materials, toys and outdoor furniture.
- Keep pets and children inside and well away from the lift.
- Have someone on site who knows where the load is going.
- Stay clear of the crane and the load while it's moving. The operator and our riggers will run the lift.
Ground and slopes
A pick and carry crane like our Franna is rated on firm, level ground. Safe Work Australia warns that a side slope of only 2 to 3 degrees can drastically affect its stability, and soft, wet or backfilled ground can give way under the wheels. Point out any soft spots, fresh fill, pits or tanks and we'll plan around them. If heavy rain or strong wind makes a lift unsafe, we'll talk to you about the safest option.
Power lines and trees
Overhead lines are the biggest hazard on a residential lift. Energy Safe Victoria's No Go Zones mean work within 3 metres of distribution lines needs the network operator's permission, and work between 3 and 6.4 metres needs a registered spotter. Tell us about every line near the street, the house and the backyard. We arrange electrical spotting where it's needed.
Quick checklist
| Check | Why it matters |
|---|---|
| Load weight and size | Decides the crane and how far it can reach |
| Photos of street, access and drop spot | Lets us plan the set-up before the day |
| Clear path and drop zone | Keeps the lift quick and safe |
| Firm, level ground | A pick and carry crane is rated on firm, level ground |
| Power lines and trees noted | Sets the safe working distance and any spotter |
| Cars moved, neighbours told | Gives the crane and the truck room to work |
| Permit if the road is used | Councils need a permit when the crane uses the road or footpath |
Sources
- Safe Work Australia, General guide for cranes: mobile cranes
- WorkSafe Victoria, Prevent pick and carry cranes from overturning
- Energy Safe Victoria, Working around powerlines
This guide is general information to help you plan a lift. Permit names, fees and timeframes can change, so check the council page before you apply. For your job, call us on 0414 649 934.