Guide

Crane permits, council by council

You need a council permit when the crane, the truck or the load sits on a road, footpath or nature strip. On private land with room to set up, you usually don't. Each council has its own permit and timeframe, and main roads go through the state. We coordinate local council permits as part of the job.

By the Ranges Rigging team Last updated

When a crane needs a permit

Councils manage local roads, footpaths and nature strips. If any part of the lift uses that space, the council wants to know about it first. That usually means one of these:

  • The crane sets up on the street, footpath or nature strip because it can't get onto the property.
  • The truck carrying the load parks on the road while we lift it off.
  • The load swings over a footpath or road, so people or cars need to be kept clear.
  • Traffic needs to be stopped, slowed or redirected while the lift happens.

If the crane can drive onto your driveway or block, set up there and lift without using the road, a permit usually isn't needed. Send us photos of the street and the property and we'll tell you which one your job is.

Which permit to ask for, by council

This table shows the permit each council in our area lists for crane work on its roads, and the timeframe it publishes. Fees change, so check the council page for the current cost. Timeframes are business days from a complete application.

Crane permits by council (as published on each council’s website, 19 November 2026)
CouncilCoversPermit to ask forTimeframeOfficial page
Yarra RangesYarra Valley and Dandenong Ranges towns, including Woori Yallock, Lilydale and HealesvilleWorks permit in a road reserve. The page lists driveway and service works, so ask council whether your crane set-up needs itAllow 10 business daysYarra Ranges council page
CardiniaPakenham, Officer, Emerald and the HillsHoarding permit (street occupancy) when machinery is used on the footpath or council property, with an approved traffic management plan. Work on the road itself needs a works within a road reserve permitUp to 28 business days for a road reserve permitCardinia council page
MaroondahRingwood, Croydon and surroundsTemporary Traffic Management Permit for works on council roads, footpaths or nature strips. A Construction Zone Permit covers longer occupationsUp to 10 business days (15 for a Construction Zone Permit)Maroondah council page
KnoxFerntree Gully, Boronia, Rowville and surroundsApproval under the Amenity Local Law to occupy council land or roadsCheck with councilKnox council page
ManninghamDoncaster, Templestowe, WarrandyteCrane permit, plus the airspace owner's consent if the crane overhangs their land10 business daysManningham council page
NillumbikEltham, Diamond Creek, HurstbridgeInfrastructure works permit, which covers occupying council land with machinery including a craneCheck with councilNillumbik council page
WhitehorseBox Hill, Mitcham, VermontPlant and Equipment Permit, with a crane lift plan and traffic management planCheck with councilWhitehorse council page
MonashGlen Waverley, Mount Waverley, ClaytonOccupy Roadway Permit, which lists mobile crane operationUp to 10 working daysMonash council page
CaseyBerwick, Narre Warren, CranbourneWorking within the road reserve permit, with a traffic management planReviewed within 10 working daysCasey council page
Greater DandenongDandenong, Keysborough, Noble ParkOccupation of Road permit for mobile cranes, generally issued for a 24 hour periodCheck with councilGreater Dandenong council page
City of MelbourneMelbourne CBD, Docklands, Southbank, CarltonPermit to use a crane in a public spaceUp to 10 business daysCity of Melbourne council page

Main roads and highways

Arterial roads such as the Maroondah Highway or the Warburton Highway are managed by the Victorian Department of Transport and Planning, not the council. It aims to respond to applications to work within the road reserve within 20 business days, so main road lifts need the most notice.

What councils usually ask for

  • The address and the exact spot the crane will set up.
  • The date and the hours of the lift.
  • A traffic management plan if traffic or pedestrians are affected.
  • Proof that the applicant holds public liability insurance.
  • For some councils, a crane lift plan showing the load, the crane and where it swings.

We take care of the crane side of this. We coordinate local council permits and facilitate traffic management, so you don't have to work out the paperwork yourself.

Power lines are a separate approval

A council permit doesn't cover power lines. Energy Safe Victoria sets No Go Zones around overhead lines. Working within 3 metres of distribution lines needs the network operator's permission, and work between 3 and 6.4 metres needs a registered electrical spotter. If there are lines near the lift, we arrange electrical spotting where it's needed.

How to keep your lift on schedule

  1. Call us as soon as you have a delivery date, especially if the crane may need the road.
  2. Send photos of the street, the driveway and where the load is going.
  3. Tell us about power lines, trees and parked cars that might be in the way.
  4. We'll tell you if a permit is needed and sort the crane side with the council.

Sources

This guide is general information to help you plan a lift. Permit names, fees and timeframes can change, so check the council page before you apply. For your job, call us on 0414 649 934.

FAQ

Questions people ask

Do I need a permit to put a crane on my street?

Yes, in most cases. If the crane, the truck or the load sits on a council road, footpath or nature strip, the council wants a permit first. Each council has its own name for it, such as a works permit in a road reserve or an occupy roadway permit. We look after the crane side of the application for you.

Do I need a permit if the crane sets up on my driveway?

Usually not. If the crane can drive onto your property, set up there and lift without using the road or footpath, a council permit generally isn't needed. Send us photos of the driveway and the street and we'll confirm which way your job goes before you book.

How long does a crane permit take?

It depends on the council. Published timeframes in our area run from about 5 to 28 business days, and the Department of Transport and Planning aims to respond within 20 business days for main roads. Call us as soon as you have a date so there's time to get it sorted.

Who applies for the crane permit?

We do the crane side. We look after the council paperwork for the crane and facilitate traffic management, so you don't have to chase the council yourself. We'll tell you early if we need anything from you, such as the owner's consent or the delivery date.

Does a council permit cover power lines?

No. Power lines are separate. Energy Safe Victoria's No Go Zones mean work within 3 metres of distribution lines needs the network operator's permission, and work between 3 and 6.4 metres needs a registered spotter. Tell us about any lines near the lift and we'll arrange electrical spotting where it's needed.

Planning a lift?

Send us photos and the load details and we'll tell you what's possible and quote the job.